Assigning Cost Resources Bug
A known bug has been found when a user follows the recommended practice of assigning a ‘Cost’ Resource to a summary task. When using the ‘Assign Resources’ dialogue if you specify the cost then click ‘Assign’ the cost will go to $0.00. In the scenario below I selected the cost resource, specified $3000.00 then pressed Read more about Assigning Cost Resources Bug[…]