Assigning Cost Resources to Tasks in Microsoft Project
Assigning cost resources to a task and tracking them is quite tricky in Microsoft Project. If you add a Work resource and a Cost resource to the same task, updating the percent completes only updates the cost of the Work resource. Let’s take a look. I have here a ‘Training’ task, assigned to Tom Henry Read more about Assigning Cost Resources to Tasks in Microsoft Project[…]