Have you ever estimated the duration for a task in Microsoft Project but wished that you could estimate real ‘Work Effort’?
For Example; I have a task that is going to take 2 days to complete however, within that two days Tom is only going to spend 2 hours on completing the task… We can model this within Microsoft Project, see below.
Interested in how EPMA can help you with your project schedules? Contact us today at 1.888.444.EPMA[email protected]